Construction Update March 2014

The Tower A exterior skeleton is now complete, with the last slab installed and work underway on the rooftop pool. Tower A architectural work is well underway up the the 22nd floor, with interior plastering, painting, M&E and ceiling installation progressing at pace. Exterior finishing & painting works continue up to the 20th floor. Waste water treatment systems are installed.

The last stages of skeletal works are underway at Tower B of The Peak Towers, with the structure built up to floor 28. Interior brick walls are set up to the 18th floor, whilst internal architectural work continues to progress up to floor 14. Construction of the Tower B waste water treatment tank is underway.

Work on the entrance road to the parking area and the drop-off route surrounding both Towers has begun.